EON AG (EOAN) and RWE AG (RWE), the country’s biggest utilities, have threatened to halt investment in wind projects unless obstacles are removed, which RWE blames mainly on slow permitting and problems with acquiring cables and transformer stations.
The difficulties undermine the government’s aim to have 10 gigawatts of sea-based turbines, or the equivalent of about nine atomic plants, installed by the end of this decade, according to the wind industry’s main lobby group. About 0.2 gigawatts were in place at the end of last year.
“We won’t reach 10 gigawatts by 2020, and everyone in the industry knows that,” Hermann Albers, the head of the BWE wind- energy lobby, said in an interview in Berlin. Grid operators, which are responsible for the connections, and their suppliers have underestimated the challenges of connecting projects that can cost upward of 1 billion euros ($1.3 billion), he said.
The sluggish start to Germany’s offshore wind expansion is a setback for Chancellor Angela Merkel’s plan to transition to a nuclear-free energy mix based on 80 percent renewable sources by 2050. It signals greater reliance on other energy sources and delays for wind-project suppliers including Siemens AG (SIE), Europe’s biggest engineering company, and ABB Ltd. (ABBN) of Switzerland, the largest maker of power-distribution equipment.
‘Not in Danger’
The German government says the delays won’t affect its goal of shutting all nuclear reactors by 2022 and raise the share of renewables to 35 percent of the total installed capacity from about 20 percent last year.
“The energy overhaul is not in danger,” as installations of land-based turbines and solar panels exceed expectations and “overcompensate” for the offshore wind delays, Juergen Maass, a spokesman for the German Environment Ministry, said by phone.
The government’s longer-term target of 25 gigawatts of offshore wind generators by 2030 “will be met, just the curve to get there may look different,” he said.
The utilities say the delays may affect longer-term commitments. Fritz Vahrenholt, chief executive officer of RWE’s Innogy unit for renewable energy, predicted a possible “collapse in investment activities” in German offshore wind farms unless the issues are resolved.
Grid Delays
Grid operator TenneT TSO GmbH told RWE that hooking the utility’s 1 billion-euro Nordsee Ost wind farm up to the grid will take 12 months longer than expected, Vahrenholt said last month in Essen, Germany, where RWE has its headquarters.
EON’s Amrumbank West project in the North Sea will be delayed by about 15 months, said Carsten Thomsen-Bendixen, an EON spokesman. The Dusseldorf-based utility said it can’t make an investment decision on two other projects in planning in Germany because of the problems.
The utilities are concerned about who will compensate them for the delays, which in the case of RWE’s Nordsee Ost farm may cause damages in the “three-digit million-euro range,” Vahrenholt said. They also want to cut red tape in permitting wind farms.
Germany’s environment and economy ministries last month set up a group that will also include grid operators, regulators and industry officials to discuss issues including permitting and liability to speed up grid connection. The group will make recommendations to Environment Minister Norbert Roettgen at the end of next month, said Thorsten Falk of the Offshore Stiftung, a wind industry lobby.
‘Exceeding Projections’
“The 10-gigawatts can be reached in principle if a broad solution for the grid connection issue can be brought on its way quickly,” Falk said in e-mailed remarks. “Whether this will be a precision landing or delayed by two years doesn’t matter for the overhaul of the electricity supply. The actual power output is what matters, not the megawatt figures. Initial experience shows that those are exceeding projections.”
TenneT has earmarked 5.5 billion euros for nine grid connection projects, Ulrike Hoerchens, a spokeswoman, said by phone. Two projects, HelWin 1 and BorWin 2, which are each able to connect several wind farms, are delayed by eight months and three months, respectively, she said.
As much as 55 additional wind farms may ask for approval in TenneT’s grid in the coming months, Hoerchens said. “That shows the kind of challenges we as a grid operator are facing,” she said.
Siemens Setback
The start of construction of the HelWin 1 converter platform will be delayed by about a year to May 2013 as the licensing and permitting process “turned out to be more complex than planned,” Torsten Wolf, a spokesman for Siemens, the main contractor for both projects, said by phone.
Siemens, which booked 203 million euros in charges in the first quarter on the delays, is “pulling out all the stops” to start construction for BorWin 2 in September, about three months later than planned, he said.
German authorities should draft a long-term offshore grid development plan and clarify who’s legally responsible to compensate for grid connection delays, TenneT said in a statement posted on its website yesterday. The operator suggested forming a “German direct-current network operator” that would plan, finance, build and operate power lines to connect the wind farms, it said.
“The current structure is not suitable to accomplish the ambitions of the energy transition,” it said.
To contact the reporter on this story: Stefan Nicola in Berlin at snicola2@bloomberg.net
To contact the editor responsible for this story: Reed Landberg at landberg@bloomberg.net
http://www.bloomberg.com/news/2012-02-20/german-offshore-wind-energy-delays-threaten-energy-plan-overhaul.html
TIME | |||||
---|---|---|---|---|---|
Sydney | Tokyo | Ha Noi | HongKong | LonDon | NewYork |
Prices By NTGOLD | ||
---|---|---|
We Sell | We Buy | |
37.5g ABC Luong Bar | ||
5,258.90 | 4,858.90 | |
1oz ABC Bullion Cast Bar | ||
4,370.80 | 3,990.80 | |
100g ABC Bullion Bar | ||
14,013.50 | 12,913.50 | |
1kg ABC Bullion Silver | ||
1,700.90 | 1,350.90 |
Powered by: Ngoc Thanh NTGold
- Online: 488
- Today: 6608
- Total: 4621884